SH23 Raglan Road rebuild works and night time closures

February 19, 2024

Work is set to start on State Highway 23 near Maungatawhiri Road from Monday 12 February for 3 weeks, with a mix of stop/go traffic management and night closures.  

 Closing the road connecting Raglan to the rest of the Waikato is the only way to undertake these much-needed works, explains Andy Oakley, Waikato System Manager at NZ Transport Agency Waka Kotahi. 

“Raglan locals will know there has been regular work at this site over the last few years to reseal the road. We’re at a stage now that a complete rebuild of this part of SH23 is needed,” says Mr Oakley.  

“Closing the highway will be an inconvenience for everyone getting in and out on Raglan. We have worked closely with our contractor to try to reduce the disruption while getting these works done as quickly as possible.

 “This is the only way into Raglan, and there is no suitable detour available. During road-closures vehicles will be escorted through the worksite at certain times. We’re confident this will help to minimise the disruption the works will cause.  

“We thank residents and drivers for their understanding and patience while these critical works are completed. I encourage everyone to check the NZTA Journey Planner on the day of their travel to see the latest road and traffic conditions before they set out on their journey,” says Mr Oakley.  

 Work on SH23 will happen across two key phases: 

Phase 1: Preparation work including kerb and channel and subsoil drainage works. This phase of the work is expected to take two weeks to complete and will be carried out during the day between 7am and 5pm under Stop/Go traffic management. This work is programmed to commence 12 February 2024 and is weather and resource dependent.

 From Monday 12 February to Saturday 24 February: stop/go traffic management will be in place between 7am and 5pm each day. This will allow crews to do preparation work, including kerb, channel and subsoil drainage works. Drivers will be able to pass through the site.  

Phase 2: From Sunday 25 February to Friday 1 March, and Sunday 3 March to Friday 8 March, SH23 will be closed between 9pm and 5am between houses #4095 and #4180, including access to Maungatawhiri Road. This will allow crews to remove existing road layers and replace them. Vehicles will be allowed through the worksite at 9.45pm, 11pm, 1am and 3am. Vehicles will need to be at the closure points at either end of the site and Maungatawhiri Road intersection at these times and will be escorted through the worksite. Once the queue is through the site the closure will re-start until the next opening time.  

 Further work to complete a second layer of seal on the road will be undertaken next summer (2024/25). 

Vehicles will be allowed through the worksite at 9:45pm, 11pm, 1am and 3am. Vehicles must be at the closure points at either end of the site and Maungatawhiri Road intersection at these times to be escorted through the worksite. Once the queue is through the site the closure will re-commence until the next opening time.

Representetatives from Fulton Hogan have said that, “Some of the machinery we use is noisy and the road will be unsealed during construction and sometimes dust can be generated. We will aim to minimise these impacts where possible.”

“Residents will have access to their properties at all times. Please approach one of the traffic controllers on site who will be happy to provide assistance if required.

“Emergency services will be given priority access at all times through the work site.

“On behalf of NZTA and Fulton Hogan Waikato, thank you for your patience and understanding while we undertake this important work within your community.”

 Plan ahead for a safe, enjoyable journey. Keep up to date with traffic updates at: journeys.nzta.govt.nz/traffic

If you have any questions or would like to speak to someone about this upcoming project, contact the 24/7 number 0800 WAI NOC (0800 924 662) to ensure they can address your concerns prior to work commencing.

from Waka Kotahi – New Zealand Transport Agency

Leave a Reply

Your email address will not be published.

The Latest Issue

The Latest Issue

Raglan Surf School

Raglan Surf School

SUPERVALUE RAGLAN

SUPERVALUE RAGLAN

Categories

Previous Story

Exercise groups thriving as more retirees choose Raglan lifestyle

Next Story

Bad Brother’s top toasties

Latest from The Chronicle

Raw another roaring success

Whilst some people around the country were indulging in  gardening over Labour Weekend as is tradition in NZ, Raglan locals and visitors